In my previous blog, I talked about
the definition of OEE, the losses associated with it and the calculation of
OEE. In this blog I’ll be talking about how to effectively use it to create an
action plan for your plant. I’ll explain the calculation of OEE
with the help of some dummy data of my plant so that everyone has a better
understanding about it.
Let’s say we have the following data
for a particular day of a month.
Date
|
Loading Time
|
Down Time
|
Operating Time
|
Total produced bale weight/day
|
Std. Cycle Time
|
Defective quality bale weight
|
Good Quality Bale weight/day
|
1
|
1320
|
200
|
1120
|
48000
|
0.022
|
1000
|
47000
|
Time is in minutes, Weight is in Kg
Let’s look at each of the above
column and how it is determined.
1. Loading Time:
Loading
Time = Available Time – Planned Downtime
Now, if we consider one day then Available time = 24 * 60
= 1440 minutes
Let’s say our Daily Preventive Maintenance is 2 hours i.e
120 minutes for my line which would be my Planned downtime. This figure varies from equipment to
equipment and industry to industry.
Planned
Downtime includes following:
·
Daily/Weekly/Monthly/Yearly PM
·
Any other major work that you are planning to do
in your equipment, line or plant for which your plant needs to be shutdown
So my Loading
Time = 1440 – 120 = 1320 minutes
2.
Down
Time:
As mentioned in my previous blog, 4
types of losses fall under downtime which are as follows:
Breakdown Loss: All kinds of stoppages whose duration is more than
5 minutes are part of Breakdown loss. Breakdown loss can be further bifurcated
into following (The bifurcation shown here is applicable to our industry but it
is more or less the same everywhere):
BREAKDOWN
LOSS
|
200
|
Mechanical
Faults
|
100
|
Electrical
Faults
|
30
|
Process
related faults
|
70
|
Utility
related faults
|
0
|
Human
Error
|
0
|
Others
|
0
|
Setup & Adjustment Loss: Changeover
loss is taken over here. Starting from the end of the previous product to the
start of the next good product. Since I’m calculating for a day, I’ve assumed
that no changeover took place and hence this loss is taken as zero.
Startup Loss: Normally when you start
your line or machine, it takes some time to reach steady conditions, hence this
loss is called startup loss. It may not be applicable in all industries like in
our case it is negligible and hence it is taken as 0.
Cutting-tool replacement Loss: The loss
incurred when you stop the machine in order to change die, cutter etc. is
called cutting-tool replacement loss. For this example it is considered to be
zero. However, in many plant this activity is normally done whenever there is
product changeover or in the PM activity. In such case it needs to be
separately shown so as to have an idea about the time taken in performing this
activity.
Thus the downtime in this case will be 200 minutes as explained above.
3. Operating Time: Operating time is nothing
but the machine run time.
Operating Time = Loading Time – Downtime
i.e 1320 – 200 =
1120 minutes
Based on the above data, we can calculate the
availability.
Availability = Operating
Time/Loading Time = 84.85%
4.
Total
produced bale weight (in Kg)/Day:
5. Standard Cycle Time:
Let’s assume that the designed capacity of the equipment shown here is to produce 65000 kg
per day.
This means 65000 kg in 24 hours i.e. 24 x
60 = 1440 minutes
Hence Std. Cycle Time = 1440/65000 = 0.022 minutes/Kg
Performance= (Actual
Output x Standard Cycle Time)/Operating Time = 94.28%
6. Defective
products:
The
defective product assumed here is 1000 Kg.
7. Good
quality products:
The good quality
products is 48000 – 1000 = 47000 Kg.
Quality
= 47000/48000 =97.91%
So now we have calculated all the three parameters which are
needed to calculate OEE: Availability, Performance and Quality.
OEE
= Availability*Perfromance*Quality
= 84.85% * 94.28% * 97.91%
= 78.32%
As mentioned in my
previous blog, merely calculating OEE is of no use to us. We need to further
analyze this OEE data and take actions based on it. Here we have obtained the
OEE as 78.32% which means that we
are having 21.68% losses in our
equipment/line.
Now, let’s look at the
following chart:
So from this data we
come to know that our major losses are our Availability losses then performance
losses and then quality losses.
If we further breakdown
availability losses, we come to know that mechanical faults have the maximum
share followed by process related faults and electrical faults. One needs to go
into detail of each of these faults, find out the reason behind the same and
then take action so as to ensure that the same fault is not repeated again.
So based on this data
you can create your action plan. You know that your OEE should be 85%, so you can set individual targets
for each of the availability losses. E.g Bring down your Mechanical faults from
100 to 50, Process related faults from 70 to 50 and electrical faults from 30
to 20.
Similarly you can set
targets for performance losses and quality losses as well once the reasons for
the losses have been known.
Thus, OEE gives you an
idea about the losses in your equipment and where you need to focus to bring
your OEE up and hence it is the most important indicator of TPM.
In
my next blog, I’ll be talking about Autonomous Maintenance Pillar of TPM.
Comments
Post a Comment